Completed for Hamilton County, this $270,000 project consisted of pipe fabrication and the installation of two new cooling towers.
Triton Services, Inc. pre-fabricated the pipe to reduce down time. This project also included the installation of a cooling tower scrubber, controls and updating the electrical system. The old equipment was removed from the roof and the new equipment was lifted with a 175 ton crane, having to block the streets to work in.
The fast track project was completed in approximately 56 hours, meeting all schedules.