Completed for Messer, this $600,000 project consisted of design and installation of site work, sanitary, storm, water and. gas utilities.
Triton relocated the 6" gas service and replaced the 60" storm sewer. The storm and sanitary pipes were both installed with layer controlled line and grade. The equipment used to complete this project was excavators of various sizes, track loaders, pad foot compactors, rubber tire back hoes and bull dozers of various sizes.
This project expanded over a 40 acre tract of land and was completed in appoxiamately 6 months, meeting all schedules.